he
key to successful interior demolition is the sometimes difficult
— but always essential — challenge of totally
containing the demolition area. Pinnacle crews have many years
of successful experience in completing all types of interior
demolition projects without in any way adversely affecting
the surrounding environment. |
| At
Bloomberg LP in New York City, Pinnacle worked with an interior
demolition contractor to prepare the firm's data center for
a new floor layout. During this project, it was crucial to create
an environment which was completely sealed off, so that there
would be no possibility of dust particles reaching the computer
area. Negative-air units were also installed in the demolition
areas to filter any dust away from operations areas. The demolition
project was completed successfully, while Bloomberg computers
continued without interruption. |
|
|